Tanks construction and installation project in Kangan refinery
Description
Tanks construction and installation project in Kangan refinery
Type
Construction of refinery fuel tanks
Project size
Construction of three fuel tanks of Kangan refinery
Employer
National Iranian Oil Refining and Distribution Company
Year of implementation
1989
Project description
Construction of three fuel tanks of Kangan refinery
Completion of executive operations and delivery to the technical group to check the welding and performance of joints
Providing the necessary machinery and equipment to execute and complete executive operations at the project site
Provide all valves and fittings required to perform executive operations and transfer them to the work site
Execution of fuel tank welding operations and installation of all connections related to tanks
Prepare required maps and designed by consultant
Complete testing of tanks and their commissioning and delivery to the employer