Construction project of gas distribution and supply network of 14 villages of Ahar - Horand Khomarloo section
Description
Construction project of gas distribution and supply network of 14 villages of Ahar - Horand Khomarloo section
Type
Construction of gas supply and distribution network
Project size
Construction of gas supply and distribution network in 14 villages
Employer
East Azerbaijan Province Gas Company
Year of implementation
2013
Project description
Supply (steel) gas supply to 14 villages of Horand district, including: Hava, Charma Dash, Viq, Jafarabad, Korn, Kavir, Arnan, Qaleh Kennedy, Tobin, Malalo, Aq Baraz, Varchin Salafi, Tabanagh, Varchin Olya
Piping 4 to 6-inch pipes with a 250-pound grid and installing fittings, flanges, valves and fittings for pool construction
Reconstruction of piping route except asphalt repair
Preparation of executive plans
Preparation and interpretation of film and radiography of pimples
Preparation of water and leakage test and resistance and test to cover the power line and eliminate all defects
All marker materials and its installation
Connection of power supply line to gas line, gas discharge and gas injection and commissioning under the supervision of the employer
The amount of crack asphalt in this contract is 2500 meters long and 10 cm thick