Construction project of gas distribution and supply network of 14 villages of Ahar - Horand Khomarloo section


Description

Construction project of gas distribution and supply network of 14 villages of Ahar - Horand Khomarloo section


Type

Construction of gas supply and distribution network


Project size

Construction of gas supply and distribution network in 14 villages


Employer

East Azerbaijan Province Gas Company


Year of implementation

2013

Project description


Supply (steel) gas supply to 14 villages of Horand district, including: Hava, Charma Dash, Viq, Jafarabad, Korn, Kavir, Arnan, Qaleh Kennedy, Tobin, Malalo, Aq Baraz, Varchin Salafi, Tabanagh, Varchin Olya

Piping 4 to 6-inch pipes with a 250-pound grid and installing fittings, flanges, valves and fittings for pool construction

Reconstruction of piping route except asphalt repair

Preparation of executive plans

Preparation and interpretation of film and radiography of pimples

Preparation of water and leakage test and resistance and test to cover the power line and eliminate all defects

All marker materials and its installation

Connection of power supply line to gas line, gas discharge and gas injection and commissioning under the supervision of the employer

The amount of crack asphalt in this contract is 2500 meters long and 10 cm thick