10-inch Khoy-Qotur gas transmission line
Description
10-inch Khoy-Qotur gas transmission line project
Project Type
Construction of 10-inch gas transmission pipeline
Project size
Construction of an 10-inch gas transmission pipeline with an approximate length of 46 km
Employer
West Azerbaijan Province Gas Company
Year of implementation
2021
Project description
The Qotur city gas transmission line, the construction of which is the subject of this contract, is branched from the 10-inch flood gas transmission line near the city of Salmas - Khoy road and continues for 46 km (horizontal length) to the Qotour city pressure reduction station.
The contractor's duties include all the necessary work for the complete installation of the gas transmission pipeline, testing and commissioning and repairing its defects.
Supply of all construction machinery and equipment and tools necessary for the construction of the pipeline, as well as supply of consumables, goods and materials, except for goods and materials, the supply of which has been entrusted to the employer according to the contract documents
Delivery and transportation of all goods and materials that are the responsibility of the employer The excuses that the contractor creates in the workshops and along the pipeline route
Implement and rehabilitate the pipeline route
Construction of access roads
Construction operations area
Leveling and paving and preparing the construction operation runway ...
Construction and complete installation of pipeline and related facilities as well as protection system
Welding of pipes and fittings according to API 1104 standard and welding method provided by the contractor and approved by the employer
Fixing defects during maintenance
Preparation of periodic reports and documents and records and maps for completed works
Perform required tests and set up