12-inch gas transmission line relocation project of Persian Gulf Mining and Metal Industries Special Economic Zone Company


Description

12-inch gas transmission line relocation project of Persian Gulf Mining and Metal Industries Special Economic Zone Company


Type

Execution of 12-inch gas transmission line relocation operations


Project size

Execution of 12-inch gas transmission line relocation operations with an approximate length of 3 km


Employer

Persian Gulf Special Economic Zone Company


Year of implementation

2013

Project description


Gas transmission line "12 companies of the Special Economic Zone of Persian Gulf Mining and Metal Industries, from TIE IN gas transmission line" 12 old located on the west side of the special zone (Hormozgan aluminum) with a length of 2858 meters until after the Bandar Abbas highway - Shahid Rajaei port at the end of the line has been the subject of executive operations and one of the duties of Keyvan Koosha Company.

The contractor's duties include all necessary work for the complete installation of the gas transmission pipeline and its testing, commissioning and repair of defects

Supply of all construction machinery and equipment and tools necessary for the construction of the pipeline, as well as supply of consumables and goods and materials, except for goods and materials, the supply of which has been entrusted to the employer according to the contract documents.

Delivery and transportation of all goods and materials that are provided by the employer to the warehouses that the contractor creates in the workshops and along the pipeline route

Implement and rehabilitate the pipeline route

Construction of access roads

Construction operations area units

Leveling and smoothing and preparing the construction operations runway, | Complete construction and installation of pipelines and related facilities, as well as the condom protection system.

Welding of pipes and related fittings according to API 1104 standard welding method

Elimination of deficiencies in the maintenance period of periodic reports and the master and swabs and maps for the work performed